The loader for The Tesorero mine. Iron ore was transported by a double aerial cable system by Pöhlig and Adolfo Bleichart which was in two sections. The one from the mine at 1,430m (4,690ft) went to a mid-way station at Corbull 1,323m (4,300ft) and the second went on to Km 108, a distance of approximately 17Km.
The highest point of the cable was 1,540 metres (5,051 ft). See map.
The cable carried buckets of 450kg travelling at a speed of 2.5m/sec (9Km/hr) totalling 40 tons/hour. The cable and loader operated between 1909 and 1915 carrying in total 170,000 tons in its lifetime. A tiny amount compared to Las Menas.
Now in very poor condition but it can still be seen how the iron ore trains were loaded and shunted.